CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Ezra Brandt is managing a software development project at Paragon Projects. Three months into the project, a major technology shift in the industry makes the original requirements less valuable. Stakeholders want to redirect the project toward emerging customer needs, but requirements are still evolving. The team has been following detailed plans with milestones set six months in advance. What should Ezra recommend?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).