CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Yasmin Kozlov is managing a temporary initiative at Quartile Advisory to develop a new client portal. Once launched, the portal will be maintained by the IT operations team. What is the PRIMARY difference between Yasmin's project and the ongoing operations?
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).