CAPM Practice: Determine how to document project controls of predictive, plan-based projects
A project team discovers a defect in a deliverable during quality control inspection. After correcting the defect, what process ensures this type of defect does not recur?
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).