CAPM Practice: Determine how to document project controls of predictive, plan-based projects
A project manager conducts a status meeting and a team member reports that her activity will be 2 weeks late. The project manager checks the schedule and determines this activity has 3 weeks of float. What action is MOST appropriate?
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).