CAPM Practice: Determine how to document project controls of predictive, plan-based projects

A project manager receives a change request that would expand the project scope. The CCB approves the change. What must happen BEFORE the additional work begins?

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).