CAPMHard
CAPM Practice: Determine how to document project controls of predictive, plan-based projects
A project manager is presenting to the project steering committee. The project is 65% complete (by EV), has a CPI of 0.88, and has 3 months remaining. The originally budgeted remaining cost was $240,000. If current CPI continues, what is the forecasted cost to complete (ETC using CPI)?
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free