CAPM Practice: Determine how to document project controls of predictive, plan-based projects

A project manager submits a change request to add 3 weeks to the project schedule due to a key resource being on medical leave. The CCB approves the change. What must happen NEXT?

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).