CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Mila Adebayo is managing a software upgrade project at Peregrine Global. The risk register identifies a critical vendor dependency with a planned mitigation strategy of weekly status calls. Mila learns the vendor prefers asynchronous updates. What is the BEST course of action?
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).