CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Mio Dlamini is executing a project at Quasar Media and notices a risk that was documented in the risk register has occurred. What should Mio do FIRST?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).