CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Emeka Nair is initiating a manufacturing improvement project at Forgepoint Manufacturing. The sponsor asks how the project aligns with organizational strategy. The project charter states the project will reduce production costs by 15%. Two similar past projects achieved 8% and 12% cost reductions. What should Emeka do to strengthen benefit planning?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).