CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Valentina Desai's project at Dawnbreak Software is using an adaptive framework. The team has been following two-week iterations with planning and review ceremonies. A major stakeholder requests a feature that wasn't in the original scope. How should Valentina respond according to the adaptive framework?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).