CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Nils Lindqvist is managing a marketing campaign project at Circuitry Labs. During benefit planning, the business case identified a 15% increase in customer engagement as the primary benefit. Three months into execution, early metrics show only 5% improvement. Several stakeholders want to abandon the planned measurement framework and switch to different metrics. What should Nils do?