Yasmin Novotny is managing a project at Gridstone AI. The risk management plan identifies a potential vendor delay. The risk occurs, and Yasmin implements the planned response strategy. What is Yasmin demonstrating?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).