CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Neha Fairbanks is managing a software development project at Vector Aerospace. The risk management plan specifies that high-impact risks require immediate escalation to the sponsor. A critical security vulnerability is discovered that could delay the release. What should Neha do FIRST?
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).