CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Florian Kobayashi is managing a software development project at Sequoia Partners. The risk management plan identifies that if server costs exceed budget by 15%, the team will switch to a cloud-based solution. Server costs have now exceeded budget by 18%. What should Florian do?