CAPM Practice: Determine how to follow and execute planned strategies or frameworks
A risk response plan identifies that if a supplier delay occurs, the project team will activate a backup vendor. The supplier notifies Solange Kwon at Wavelength Biotech of a two-week delay. What should Solange do?