Skip to content
CAPMMedium

CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Irina Khoury is working on a project at Quasar Media where a new risk has been identified. The risk register indicates the response strategy is 'mitigate.' What action should Irina take?

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free