CAPM Practice: Determine how to plan project iterations
A team is mid-sprint and realizes that completing the sprint goal will require more work than estimated. The team should:
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).