CAPM Practice: Determine how to plan project iterations
A product owner prioritizes a backlog item rated 'must have' by stakeholders but only worth 5 story points (simple to implement). Another item is 'nice to have' but worth 200 story points (large and complex). In value-based prioritization, which should be worked on first?
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).