CAPM Practice: Determine how to plan project iterations
During sprint planning, the team determines they can take on 40 story points. The product owner has 60 story points of priority backlog items. What determines which 40 points are brought into the sprint?
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).