CAPM Practice: Determine how to prepare and execute task management steps

An adaptive team has been using a digital task board for 6 months. During a retrospective, they identify that the board has become cluttered with old cards in ambiguous states, the WIP limits are rarely enforced, and nobody updates cards consistently. What underlying issue does this reveal and what should be done?

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).