CAPM Practice: Determine how to prepare and execute task management steps

An adaptive team is using a digital Kanban board. A team member updates card status by moving it to 'Done' but has not met all definition of done criteria. What should happen?

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).