CAPM Practice: Determine how to prepare and execute task management steps

An adaptive team identifies a story that has external dependencies on another team who will not deliver until next sprint. During sprint planning, should they select this story?

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).