CAPM Practice: Explain the components of an adaptive plan
An organization is transitioning to adaptive planning and wants to know whether they need to abandon all their existing planning documents (business cases, project charters, governance reports). What is the BEST advice?
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).