CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
A defense contractor is awarded a contract to build specialized communication equipment according to military specifications. The specifications are exhaustive and changes require joint approval from the contractor and the military customer. What approach BEST fits this scenario?
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).