CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

An organization is evaluating whether to use predictive or adaptive for a multi-year enterprise resource planning (ERP) implementation. The ERP vendor provides a fixed implementation methodology with defined phases. The business processes to be replaced are well-documented. Some customization will be needed. What is the MOST appropriate approach?

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).