CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

An oil and gas company is planning a new pipeline installation. The project has regulatory permits that define exact specifications, fixed contracts with contractors, and must cross multiple jurisdictions with different approval processes. What approach is MOST appropriate?

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).