CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
A project has been running for 6 months in predictive mode. The project manager wants to confirm the project is still aligned with the original business justification. What document should she review?
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).