CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach
A client insists that a complex aerospace system be delivered using a predictive approach. Requirements are fully documented in a 500-page specification document reviewed and approved by all stakeholders. This is MOST consistent with:
Key Concept
This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).