CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

A project sponsor asks whether a predictive or adaptive approach is better for a manufacturing quality improvement project. The process being improved is well-documented, the desired outcome is clearly defined, and regulatory compliance requires audit trails. The project manager should recommend:

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).