CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

A project manager must select an approach for a software integration project. The integration connects two legacy systems using well-documented APIs, has fixed contractual deliverables with a government agency, and must be completed within a non-negotiable regulatory deadline. The team is experienced with both systems. What approach is MOST appropriate and why?

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).