CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

An infrastructure company has historically used predictive project management successfully. They are considering applying the same approach to a new digital transformation initiative involving emerging AI technology with no internal precedent, user adoption that depends on behavioral changes, and uncertain integration with existing systems. What is the MOST appropriate recommendation?

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).