CAPM Practice: Explain when it is appropriate to use a predictive, plan-based approach

A project manager is assigned to a 3-year, $50M highway construction project with approved engineering drawings, fixed-price contracts with subcontractors, and defined regulatory milestones. Midway through, a stakeholder requests a design change that would require revising 30% of the completed structural work. Using a predictive approach, what is the CORRECT sequence of actions?

Key Concept

This question covers Explain when it is appropriate to use a predictive, plan-based approach under Explain when it is appropriate to use a predictive, plan-based approach (Predictive, Plan-Based Methodologies).