CAPM Practice: Explain when it is appropriate to use an adaptive approach

An organization is transitioning from predictive to adaptive project management. A project manager who has managed predictive projects for 15 years is struggling with the transition. Which challenge is she MOST likely to face?

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).