CAPM Practice: Explain when it is appropriate to use an adaptive approach

A project manager is evaluating whether to use Scrum or Kanban for a maintenance team that handles incoming support tickets of varying priority. Which approach BEST fits?

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).