CAPM Practice: Explain when it is appropriate to use an adaptive approach

A product owner has 50 items in the product backlog. The team's velocity is 10 story points per sprint, and the total backlog represents 200 story points. If the release date is in 15 sprints, what is the approximate capacity for backlog items?

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).