CAPM Practice: Explain when it is appropriate to use an adaptive approach

A product development team is deciding between predictive and adaptive. Their product is a new consumer app in a fast-moving market where competitor products launch monthly. The right feature set is unclear. Which consideration MOST strongly supports adaptive?

Key Concept

This question covers Explain when it is appropriate to use an adaptive approach under Explain when it is appropriate to use an adaptive approach (Agile Frameworks/Methodologies).