Skip to content
PMPEasy

PMP Practice: Communicate risk status to stakeholders

Kavya Subramaniam is managing a municipal water treatment facility upgrade for Kaito Fujimoto Partners. During risk assessment workshops, the team identifies a significant risk: potential discovery of contaminated soil during excavation, which would trigger mandatory environmental remediation. The team estimates three scenarios: best case remediation cost of $45,000 (20% probability), most likely cost of $85,000 (50% probability), and worst case cost of $140,000 (30% probability). Kavya needs to calculate the expected monetary value of this risk to determine the appropriate contingency reserve allocation. What is the EMV for this risk?

Key Concept

This question covers Communicate risk status to stakeholders under Assess and Manage Risks (Process).

This is 1 of 100 free PMP questions

Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.

Unlock All Questions