PMP Practice: Ensure Shared Vision with Stakeholders
Naledi Dlamini is leading a project at Hanami Robotics to develop a voice-activated accessibility app for smart home devices. The business sponsor envisions the app as 'revolutionizing home accessibility,' while the UX team wants to 'create the most intuitive interface possible,' and the engineering lead is focused on 'maximizing device compatibility.' During the project kickoff, team members express confusion about what success looks like, and different groups have begun working toward their own interpretations. The organization has successfully used adaptive approaches on similar consumer-facing projects. What should Naledi do to establish a shared vision?
Key Concept
This question covers Ensure Shared Vision with Stakeholders under Develop a Common Vision (People).