PMPMedium
PMP Practice: Update Documentation for Changes
Ziggy Okonkwo-Petersen is managing a warehouse automation project for Barakah Biotech using a predictive approach. During execution, the operations director submits an urgent request to add real-time temperature monitoring for pharmaceutical storage—a capability not in the original scope. The operations director insists this feature is critical for a new client contract worth $8M annually and claims the CEO verbally approved it last week. Ziggy checks the project charter and scope baseline, which do not include this functionality. The change would require an additional 6 weeks and $240K. The project is currently on schedule and within budget, but the team is fully allocated. What should Ziggy do FIRST?
Key Concept
This question covers Update Documentation for Changes under Manage and Control Changes (Business Environment).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions