Ocean Reyes is leading a hybrid project at Sourdough Signal Corp to develop a mobile app with both new features and infrastructure upgrades. The team uses two-week sprints for feature development and follows a predictive approach for infrastructure work. During the retrospective for Sprint 3, three team members independently report that recent API integrations are failing quality checks at a rate of 35%, causing significant rework. The team has already completed root cause analysis and identified that inconsistent API documentation from the infrastructure team is the primary cause. What should Kenji do next?
Key Concept
This question covers Recommend options for improvement based on quality gaps under Plan and Manage Quality of Products/Deliverables (Process).