River Tanaka is managing the construction of a renewable energy training facility for Ocean Volkov Partners. During schedule planning, the sponsor asks how long similar projects have taken to complete. The organization has built four comparable training facilities over the past three years. River has not yet reviewed the historical documentation from these projects. What should River do to respond to the sponsor's question?

Key Concept

This question covers Measure ongoing progress based on methodology under Plan and Manage Schedule (Process).