Activity Attributes
Activity attributes are additional details associated with each schedule activity that extend the description beyond what is in the activity list.
Explanation
Activity attributes expand on the information in the activity list by providing detailed characteristics for each activity. Early in the project, attributes may include only the activity identifier, WBS ID, and activity label. As the project progresses through planning, additional attributes are added such as predecessor and successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
These attributes are essential inputs to the Sequence Activities and Estimate Activity Durations processes. For example, predecessor and successor information drives the creation of the project schedule network diagram, while resource requirements feed into resource planning and duration estimation. Activity attributes also support schedule reporting and sorting, allowing the team to filter and group activities by various criteria.
Activity attributes are documented and updated throughout the project as part of progressive elaboration. They are closely tied to the activity list and are often maintained in the same scheduling tool or database.
Key Points
- •Extend the activity list with detailed characteristics for each activity
- •Include predecessor/successor relationships, leads, lags, constraints, and resource needs
- •Evolve over time through progressive elaboration
- •Support schedule network diagramming, estimation, and reporting
Exam Tip
Activity attributes grow in detail as planning progresses. Early on they may just have an ID and name; later they include dependencies, resources, and constraints.
Frequently Asked Questions
Related Topics
Activity List
The activity list is a comprehensive list of all schedule activities required on the project, including an activity identifier and a scope of work description for each activity.
Define Activities
Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Leads and Lags
A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.