Skip to content
PMPCAPM

Contingency Reserves

Contingency reserves are budget amounts allocated within the cost baseline to address identified risks that have been accepted and for which contingent or mitigating responses have been developed.

Explanation

Contingency reserves are funds set aside to handle identified risks, also referred to as "known unknowns." These reserves are included in the cost baseline and are under the control of the project manager. They represent an estimated amount needed to address specific risks if they occur.

Contingency reserves can be estimated using various methods, including a percentage of the estimated activity cost, a fixed amount, or through quantitative analysis techniques. As the project progresses and identified risks either occur or are retired, the contingency reserves are adjusted accordingly.

The project manager has the authority to use contingency reserves without requiring a change request because they are part of the cost baseline. However, the project manager must document the use of these reserves and report on the remaining balance. This is different from management reserves, which require a change request for use.

Key Points

  • Allocated for identified risks (known unknowns)
  • Included within the cost baseline
  • Managed by the project manager without change requests
  • Adjusted as risks are resolved or retired throughout the project

Exam Tip

Contingency reserves are part of the cost baseline and are controlled by the project manager. They address known unknowns. No change request is needed to use them.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.