CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project manager is developing a schedule for a complex project with 250 activities. She discovers that 45 activities have the same late finish date as the project end date and zero float. This means:
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).