CAPM Practice: Demonstrate an understanding of a project management plan schedule
In a project schedule, a 'summary activity' (also called a 'hammock activity') represents:
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).