CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Camilo Sesay is planning problem-solving activities at Eastbound Logistics. Match each technique with its PRIMARY purpose. Items: 1. Daily standup meeting 2. Brainstorming session 3. Focus group 4. Retrospective meeting Which option correctly matches each item to its description?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).