Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Maryam Ashworth is leading a problem-solving session at Forgepoint Manufacturing to address recurring quality issues. The team quickly agrees on the first proposed solution. What should Maryam do?

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free