CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

A project team is struggling to reach consensus on which of five proposed solutions to implement. The facilitator asks each member to independently rank the solutions, then aggregates the rankings. This is an example of:

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).