Andres Baranov is developing the project schedule for a clinical trial at Wavelength Biotech. The regulatory approval submission is marked as a milestone, while 'conduct patient screenings' is shown as a task with a 30-day duration. What is the key difference between these two schedule elements?

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).